Penny Place Apartments Construction Update September 2020

img

This is where Maxcon and the construction team are at on Penny Place Apartments as at the end of September 2020.

  • Level 21 windows commenced
  • Level 21 balustrade & A/C boxes installed
  • Level 20 plaster now complete
  • Level 20 services (rough-in) now complete
  • Joinery installed to Level 18
  • Level 15 stone installed
  • Level 13 tiling commenced
  • Services second fix complete to Level 14
  • Splashbacks installed to Level 14
  • Bin chutes installed to Level 14
  • FFE installed to Level 13

Completion is expected early Q2 2021.