31.03.20

Penny Place Apartments Construction Update March 2020

img

Maxcon continued works during March with the construction works status as follows:

  • Level 3, 4 & 5 slabs were poured
  • Ground Floor block work completed
  • Services for Ground Floor are 80% completed
  • Level 1 fire sprinkler works commenced
  • Precast core to Level 5 installed
  • Formwork to Level 6 commenced

 

The key milestone achieved during March was the topping out of the podium, works can now proceed on the tower structure.
 