Penny Place Apartments construction update for January 2021, during the month Maxcon undertook the following works:
• Commission and completion of internal building lift
• Penny Place entry signage installed
• Carpark line marking and concrete sealing complete
While fitout progress included:
• Level 20 - 23 Builders Defects & Clean
• Final detail paint touch ups to Level 6 – 12
• Final detail defect close out Level 6 – 12
• Level 23 bin chutes installed
• Corridor carpet installed Level 12 – 23
Completion is expected mid April 2021.