Penny Place Construction Update for August 2020

Completion expected Q2 2021.

Maxcon continued works during August completing Level 18 to Level 22 concrete slabs with Level 18 formwork stripped. Level 21 insitu columns poured.

Services works to Level 1 – 4 completed with sewer stacks, fire sprinklers and permanent lights. The carpark screen installed on all elevations except for Alimak area. 

In addition, both precast panel cores installed up to Level 22 with internal core stairs poured to Level 17.

Fitout progress includes: 

  • Level 12 - 17 plaster walls and ceiling installed with first coat of paint
  • Level 14 - 18 balustrade completed including painting of balcony soffits 
  • Level 14 - 17 A/C enclosure boxes completed
  • Windows to Level 14 - 18 installed including all carpark windows
  • Level 10 tiling completed 
  • Level 11 tiling commenced 
  • Joinery to Level 13 installed 
  • Stone benchtops to Level 11 installed