29.06.18

Kodo Construction Update

img

Kodo construction status as at July 2018.

Jump form at Level 28
Floor Level up to Level 24 part poured
Structural Steel Level 24 complete
Formwork is at Level 24
Reinforcing to Level 24 completed
Fitout is at various stages through Level 2 to 20
Façade to Level 20 completed

Flagship Property Holdings